What’s next

After our first stage of consultation closes, we will consider all the feedback we have received and, together with our ongoing technical studies, use that feedback to help us shape our proposals.

Indicative timeline

2022

  • Summer 2022 – First stage of consultation on Mona offshore wind farm
  • Autumn 2022
    • Ongoing technical and environmental work
    • First stage of consultation on Morgan offshore wind farm
  • Winter 2022 / 2023 – Second stage of consultation

2023 & 2024

  • Winter 2023 / 2024 – Applications submitted for Development Consent Order (DCO) and other licences

2025

  • Expected decision on the DCO by the Secretary of State

2026

  • Expected Final Investment Decision (FID)

2027

  • First grid connection for power export commissioning of offshore substations

2028

  • Expected start – Commercial Operation Date (COD)

Public consultation
7 June to 3 August 2022

Find out more about what we're consulting on and how you can take part.